Site Visit: Nuneaton

George Sands was on site last week to attend Parkway Construction MK Limited‘s site meeting and review on site progress so far at Tungsten Properties‘ Bermuda Park in hashtag#Nuneaton. 🚧🚧

With access road laid this week, the warehouse floor, internal walls, car park paving complete and the yard and cladding almost finished, it is exciting to see the progress move along so well!

The development will deliver over 36,730 sq ft (3,412 sq m) of top quality industrial / logistics space to the market! πŸ‘πŸ‘

The scheme is aiming to achieve:
βœ… BREEAM Excellent
βœ… EPC A rating
βœ… 10 metre eaves height
βœ… 3 Ground level loading doors
βœ… Secure self-contained yard
βœ… Fully fitted offices

Many thanks to Parkway Construction MK Limited, PRP UK Ltd, Goodrich Consulting LLP and CA Group for their effort so far and George Sands, Nigel Teal and David Wainwright from HTC Architects for all their hard work!

With practical completion anticipated for just before Christmas, we are excited to see the finished results before the year ends! πŸ™ŒπŸ™Œ

LinkedIn Post: https://www.linkedin.com/feed/update/urn:li:activity:7391048241846575104